Project:
SPGFD- PHASE 22-24, Metrology, Spool Fabrication, Transportation, Installation and Pre-commissioning of 32″ & 4″ offshore pipelines
Client:
Pars Oil and Gas Company - POGC
Location:
South Pars Gas Field – Persian Gulf, Iran
Purpose:
Metrology, Spool Fabrication, Transportation, Installation and Pre-commissioning of phase 22-24 spools
Scope of work:
The scope of work was to carry out the metrology, fabrication of 32-inch and 4-inch spools, transporting the spools from yard to offshore site, installation of Spools, Pre-commissioning and hydro-test of 32-inch and 4-inch piggy back pipelines of phase 22 South Pars gas field development project.